Building Owner: Deleted
Address: Deleted
Job Number: 574
Project Scope of Work:
Project is a 64 unit condominium single structure 4 story building. Existing
roof is 3 tab fiberglass shingles with galvanized metal roof flashings and
vents. Scope of work involves the complete removal of all galvanized metal roof
flashings including valleys, vents, lead stacks and expansion joints. Existing 3
tab shingles are to remain. New 26 guage galvanized 3X3 drip edge with polyester
coating is to be installed at all perimeters color is white. New lead stacks are
to be installed at all PVC pipe vent penetrations. New 26 guage galvanized metal
roof vents are to be installed. New 26 guage galvanized 16" valley is to be
installed. New expansion joint with neoperene baffle to be installed where
currently sheet metal expansion joint exists, expansion joint to be installed in
accordance with manufacturer recommendations. New 40 year dimensional shingles
to be installed with 1-1/2" galvanized ring shank nails, 6 nails per shingle, in
full accordance with manufacturer installation instructions. If pneumatic
equipment is utilized for the installation of shingles, nails manufactured by
Paslode will be required. Shingle manufacturer 40 year warranty will be
required. All major shingle manufacturers that fulfill warranty requirements
will be considered. Color to be determined.
Special Notes/Conditions/Housekeeping
Bidding contractor to verify all field dimensions and existing conditions to
fully comply with the specifications. Existing structure is wood trusses with ˝"
plywood sheathing, 30# felt nailed and tin tagged to plywood with 3 tab shingles
nailed. Project site must be maintained clean and organized at all times. No
debris shall be stocked, all debris must be placed directly into a refuse
container.
Roofing Consultant:
This project is being overseen by E-Roof Solutions, Inc., as Owners
Representative, any and all questions are to be directed to tech@eroofsolutions with the job number
574 PROMINENTLY DISPLAYED. If e-mail is not available inquiries may be faxed to
954-474-3210. E-mail inquiries are usually answered within a few hours.
Site Conditions:
It is the responsibility of the bidding contractor to completely familiarize
himself with all existing conditions. Any damage to the property caused directly
or indirectly by the roofing contractor must be repaired to original condition
at the expense of the roofing contractor.
Current Building Use:
Current use is a residential condominium. All roofing operations will be
conducted from the front of the building. Parking lot will be cleared with 48
hours notice to the Owner of commencement of the work. SAFETY OF ALL INVOLVED
TAKES PRECEDENT OVER ALL OTHER CONSIDERATIONS.
Insurance Requirements – Contractor Qualifications:
Minimum insurance requirements of 1,000.000.00 general liability per
occurrence and statutory workers compensation. Certificates listing the Owner as
additional insured are required. Certificates must be issued and received 7 days
prior to start of work, NO WORK WILL BE CONDUCTED PRIOR TO RECEIPT AND
VERIFICATION OF INSURANCE COVERAGE. Contractor must be an approved
applicator for the roofing system manufacturer utilized, verification of
approval and a copy of application for warranty must be provided to Roof
Solutions prior to commencement of the work. If application for warranty is made
electronically a printed copy of application may be faxed or e-mailed.
Payment:
Payment for project number 574 will be in full upon completion, final
inspection by Owner, Consultant and local governing building department and
issuance of required manufacturer warranty paperwork. In the absence of final
warranty paperwork an amount of 15% of the contract amount will be held pending
issuance of the warranty. If Contractor produces a letter from the system
manufacturer that the project number 574 has been inspected and passed and the
warranty is forthcoming the withheld amount will be reduced to 5%. No funds will
be disbursed for this project prior to completion.
Bonding:
No bid, payment or performance bond is required for project 574.
Permits:
It is the responsibility of the contractor to obtain and pay for all permits,
licenses and approvals necessary for the completion of the work.
Scheduling:
Commencement of the work shall be within 20 days of contract award and
completion 30 days thereafter. 5 days of inclement weather delays are
incorporated in the 20 day completion allowance.
Existing Site Conditions:
Power is available. Restroom facilities must be provided by roofing
contractor.
Consultant/Owner Inspections:
From time to time during the course of this project photographs will be
taken, these photographs will be utilized to verify compliance with the scope of
work, manufacturers specifications and to provide documentation of proper
completion of the work. These photographs will include review of equipment
utilized for the completion of the work and verification that the equipment is
at its proper setting. Contractor shall provide 48 hours notice to Owner of
material loading on project and commencement of work. Upon notification by
Contractor of final completion the Owner will complete final inspection of the
work and structure to confirm adequate clean up and preservation of the
structure. Any work not in full and complete compliance with the manufacturer’s
specification will not be accepted, repair and replacement of defective work
will be the responsibility of the Contractor.
Guarantees/Warranties
The contractor shall guarantee the work to be free from defects in material
and workmanship for a period of 4 years from date of completion. Shingle
manufacturer 40 year warranty is required. The Contractor is required to repair
any and all defects in material in workmanship even if said defect are not the
direct cause of a leak.
Project Supervision:
The Contractor will maintain at all times during the course of the work a
competent english speaking experienced knowledgeable Superintendent.
Material Storage/Equipment:
All material shall be stored in a neat dry condition in original manufacturer
packaging. Damaged material will not be accepted. All equipment will be in full
safe complete operating condition. All equipment must be in full safe
operational condition in compliance with O.S.H.A. standards.
Code Requirements:
This project must comply with SBCCI, South Florida Building Code. All
materials must have Dade County Product Approval.
Building Department Jurisdiction:
Collier County
Submittals:
Required for project 574, sample of ASTM 30#, sample of nails, cut sheet on
shingles including installation instructions, cut sheet on nails, cut sheet on
vents, cut sheets on expansion joint. Submittals should be submitted in smallest
practical sections no later than 7 days after notice of award to ERS.
Notice of Commencement:
Notice of Commencement will be provided by Owner to successful
bidder.
Proposal:
Proposals in the bidders format are acceptable. Reference must be made that
proposal is in accordance with scope of work in strict accordance with
manufacturer specifications. Proposal must clearly state proposed system
manufacturer. Provide unit pricing for square foot deck (plywood) repair and
replacement and lineal foot fascia repair (2X8 Cedar). Provide alternate price
for 30 year dimensional shingle in lieu of 40 year. In the alternative provide
hourly rate for journeyman roofer, helper, laborer. Proposal shall be valid for
60 days from date of issue. The Owner reserves the right to reject any and all
bids without cause. Proposals should be faxed to 954-474-3210 or e-mailed to proposal@eroofsolutions.com any
commonly recognized format is acceptable.
Code/Specification Conflict:
It is the intent of this scope of work to provide this Owner with the most
cost effective, technically correct roof installation available in full
compliance with State and Local Building Codes. If any conflict occurs the more
stringent provision will take precedence.
Safety:
A safe project for the Owners and Contractors personnel takes precedent over
all other considerations. Contractor is responsible for compliance with all
applicable O.S.H.A. standards.
End Project 574